Emerald Park update: Fall 2013 edition
We are now forming the 13th floor at Emerald Park and we are working at a rate of 1.1 floors per week. Our goal is to be on the 31st floor by the time we break for Christmas. Continue reading
Emerald Park Condos reaches 7th floor
We’re pleased to report that we have met the goal we had set out in our last update to have Emerald Park reach typical by the end of July. Continue reading
Construction update: Turning up the heat at Emerald Park
Before we get into this months update, we’d like to start by giving a special mention to the TMG construction crew who have been working hard at the site in the middle of the summer heat. Continue reading
Construction Forging Ahead at Emerald Park!
We set a new record at Emerald Park this month! In June we pumped more concrete and placed more steel than we’ve done in any other month, so work is progressing quite well and everyone is working together to reach our goals. Continue reading
Emerald Park is moving up
May is here! That means it’s time for another update from Emerald Park. Continue reading
Emerald Park spring update
Spring is here? Already? Feels just like yesterday when we posted our Emerald Park condos winter update. Time sure is moving quickly. So is the new construction at Emerald Park. Here’s what we’ve been up to lately. Continue reading
Emerald Park winter update
It’s time for another update from Emerald Park! Continue reading
Emerald Park rises above ground
Latest construction news from Emerald Park
We’re back with another construction update from Emerald Park! Continue reading