First Emerald Park construction update

June 8th, 2012

In the midst of all the buzz and excitement over E Condos, don’t forget about our other landmark project, Emerald Park! With it’s unique design, Emerald Park will make a dramatic statement at Yonge and Sheppard once it’s complete, and the building is sure to turn heads.

Here’s a reminder of what it will look like.

So where are we with construction? Here’s an update with a couple of photos from the site.

The original excavation is complete and the tailings from the remaining footings are being taken out at the moment. There are also currently two tower cranes on site and the excavator will be removed in a few weeks.

The pour has started at P3 of building B (west side of the site). In addition, all shoring has just been completed and deep foundations will be finished by June 11th.

The underground drainage and slab on grade will commence once the excavator work is done.The west side will be at grade in August while the east side will be at grade in the Fall.

The next big job on site is the large concrete pour on the floor podium which will commence in a few weeks.