Like many construction sites across the city, we too have been affected by the extreme cold weather conditions and this has led to some construction delays.
At the beginning of this year, Emerald park was barely above ground level and the crane had just gone up. Fast Forward to the end of the year, and we’re now working on the 24th floor on one side, and the 26th floor on the other. How time flies!
In our last update, we promised that we’d start installing the windows in late October, and we’re pleased to report that we’re right on schedule! Over the past few weeks, we’ve been busy installing the windows on the residential levels of Emerald Park.
We are now forming the 13th floor at Emerald Park and we are working at a rate of 1.1 floors per week. Our goal is to be on the 31st floor by the time we break for Christmas.
We’re pleased to report that we have met the goal we had set out in our last update to have Emerald Park reach typical by the end of July.
Before we get into this months update, we’d like to start by giving a special mention to the TMG construction crew who have been working hard at the site in the middle of the summer heat.
We set a new record at Emerald Park this month! In June we pumped more concrete and placed more steel than we’ve done in any other month, so work is progressing quite well and everyone is working together to reach our goals.