Construction Update: Exhibit

We’re making lots of progress at Exhibit, our development at Bloor and Avenue Road. It’s been almost a whole year since we updated you last – time flies! – and lots has happened in the interim. We’ve gone from the ground floor:

IMG_2200

…to the 17th floor! This floor is the beginning of the third cube, which rotates slightly to the northwest on top of the second cube.

 

20150617_091014

20150617_091027

 

Residential windows have been added up to the 7th floor,  and suite framing has started up to the 6th floor. In the lobby area, curtain walls have been added:

 

20150616_135533

The parking garage is also in the midst of the framing process – you can see here that it’s been laid out in steel.

20150616_140254

The parking garage and the first two cubes also have completed electrical and mechanical rough-ins.

We’re delighted to be on-schedule and making steady progress on this building – stay tuned for more updates, and follow along on Twitter so you won’t miss a thing.

 

 

The Latest from the TTC

It has been a great year for the TTC with lots of new changes and announcements. Our buildings that are currently under construction are in some major transit hot-spots and any changes to the TTC will have an effect on our purchasers day-to-day lives, so we want to give you a run-down of what’s new. Continue reading