Demolition Snapshot: One Yorkville

If you’ve been to Yorkville lately, you’ve probably seen that we’re making progress on one of our most anticipated and luxurious communities – One Yorkville!

This statuesque tower will one day be home to world-class amenities, two roof decks, a stunning sculptural facade and a location minutes from world-class shopping on Bloor St. and the TTC to take you anywhere. Plus, the original storefronts will remain intact! For now, though, we’re going into 2016 with a clean slate. Continue reading

Emerald Park’s Completed!

We’re beyond excited to announce that Emerald Park is finally completed!

This stunning emerald green tower was designed to be enticing, exotic and stand out from the grey monotony of North York’s skyline. All 564 units in these towers (42 and 33 storeys, respectively) are sold out! We’re so proud that the design risks we took with these towers are as stunning in real life as they were on paper. Continue reading

October Update From E Condos: Watch Our Raft Pouring

We have so many exciting updates coming out of our bustling E Condos site at Yonge and Eglinton! Now that the crane is in and the foundation is laid, we’re all ready for the next stage – the raft pour.

In the below video, you can see our bustling site after night falls, where we’re pouring concrete to create the raft slab. Make sure you hit HD so you don’t miss a thing!

 

 

A raft slab, or raft foundation, is a style of foundation that uses steel bars to reinforce cement for a super-strong and durable base. This is one in several steps we have to take to ensure that E Condos will be safe, strong, and standing for years to come. It won’t be long until we start to develop above ground, but for now we’re not cutting any corners in ensuring our foundation is as strong as we can make it.

Want to know more about our upcoming projects? Contact us! 

Is one of our developments your future home? Make sure you’re following us on Twitter for all the updates!

October Construction Update: E Condos

Welcome to the October construction update for our Yonge and Eglinton project, E Condos! We’re so excited for this development to begin taking shape, and now that our crane is in, progress is coming faster than ever! You might remember about a month ago, we shared this mini construction update where we explained how to install a crane: Continue reading

June Construction Update: E Condos

Progress at the E Condos site is coming along faster than ever – it’s already time for another construction update! If you missed the previous one,  click here to catch up. We’ve made some major progress in the month of June and, while we’re still in early stages, the site is in great shape and moving on time.

The structural caissons in the E8 (South Tower) raft slab was completed. The shoring work at this slab is currently in progress. Excavation of the third underground floor at the South Tower is also resuming this week. Continue reading

Construction Update: Exhibit

We’re making lots of progress at Exhibit, our development at Bloor and Avenue Road. It’s been almost a whole year since we updated you last – time flies! – and lots has happened in the interim. We’ve gone from the ground floor:

IMG_2200

…to the 17th floor! This floor is the beginning of the third cube, which rotates slightly to the northwest on top of the second cube.

 

20150617_091014

20150617_091027

 

Residential windows have been added up to the 7th floor,  and suite framing has started up to the 6th floor. In the lobby area, curtain walls have been added:

 

20150616_135533

The parking garage is also in the midst of the framing process – you can see here that it’s been laid out in steel.

20150616_140254

The parking garage and the first two cubes also have completed electrical and mechanical rough-ins.

We’re delighted to be on-schedule and making steady progress on this building – stay tuned for more updates, and follow along on Twitter so you won’t miss a thing.