We’re pleased to report that we have met the goal we had set out in our last update to have Emerald Park reach typical by the end of July.
Construction is going according to schedule and both towers at Emerald Park have completed the 7th floors. We are now working on the 8th floor.
95% of the basement work is completed except for painting, traffic topping and a few miscellaneous items.
We have been working on erecting man/material hoists and blocking in the ground floor loading docks.
Now that we’ve reached typical, the goal for the next few months is to complete as much as possible before the end of the year.