July Construction Update: Exhibit

August 12th, 2015

Summer’s in full swing, and with long, hot days has come tons of construction update at Exhibit! Last time we updated you, we were on top of the world on the 17th floor:

toronto skyline

Things have only gone up from there! We’re currently on the 19th floor (cube 3) pouring the concrete floor slab.

We’re also working from the top up on all the fun details. We’ve installed windows up to the 8th floor, and balcony railings up to the 2nd floor.

We’ve also started the ground floor curtain walls. Curtain walls are the frames that hold the windows and siding into the facade of the building. Glazing will follow when that’s complete, and then the exterior will really start to take shape! While we’re at it, we’re also installing parking garage windows.

exhibit condo construction

toronto condo construction

 

Plus, BlacktowerTV stopped by the site last weekend and sent us this update shot – from this angle, you can see the cube rotation starting to take shape.

That’s it for our July condominium construction update! Have you been by the site?