May is here! That means it’s time for another update from Emerald Park.
Since the start of the year, we’ve made great progress with moving Emerald Park up and we’re currently focused on getting the building up even more floor by floor.
We’re moving up at a much faster pace now at the site. We’re currently pouring the first half of the 3rd floor on the West tower and 100% of the 2nd floor pours are done. In addition, 85% of all the verticals are also complete from the 2nd and 3rd floor.
The underground is fully cleaned and we’re awaiting bricklayers and painters to come in and begin work there which we expect to start in two weeks time.
The waterproofing around the exterior slab is 90% complete and we’ll be looking to get that fully finished as soon as possible. Then it’s a case of adding floors on as best we can.