June Construction Update: E Condos

July 6th, 2015

Progress at the E Condos site is coming along faster than ever – it’s already time for another construction update! If you missed the previous one,  click here to catch up. We’ve made some major progress in the month of June and, while we’re still in early stages, the site is in great shape and moving on time.

The structural caissons in the E8 (South Tower) raft slab was completed. The shoring work at this slab is currently in progress. Excavation of the third underground floor at the South Tower is also resuming this week.

20150602_114533 (800x450)

 

The previous temporary hydro lines were also replaced with a permanent connection to better service the site. This connection will one day bring power to E Condos residents!

20150617_133255 (450x800) (1)


20150601_092440 (450x800)

20150604_102457 (450x800)

In our last report, demolition at 31 Roehampton was still in progress. Now, that demolition is complete and shoring work is beginning! This is the future site of E15, the North Tower.

20150624_083118 (800x450)

Interested in learning more about E Condos? Follow us on Twitter for updates, or call us at 647-343-3377.